Vehicle Manufacturing Plant, West Midlands
• 38,000 sq metres Vebro 6mm Pump Screed and Coating
• 480 tonne Vebroscreed Pump Screed Installed
• 20 tonne of liquid primer rolled by hand
• 20 tonne of liquid top coat rolled by hand onto the level screed

Each week 3000m²-5000m² was completed in 6 days and on day 7 we were given the next phase to start.
____________________________________________________
Electricity Distribution Network, Swansea
• 2800 sq metres Sikafloor 377/359 System
• 650 lm Cove Skirting 
• Sikagard 63N 5 coat Fibre Glass Bund Lining System
_____________________________________________________
Rail Depot, Exeter
•  3900 sq metres Sika Multidur Broadcast System
•  900 sq metres Sika Wall Coating
_____________________________________________________
University Film Studios, Leeds
• 1500 sq metres Remmers Optiplan
•  800 sq metres of Remmers Epoxy ESD SL Screed
____________________________________________________
Hospitals, Chelsea & Cambridge
• 1400 sq metres Sika Level Screed and Sika Comfortfloor
•  600lm Cove Skirting
•  4300 sq metres Schonox XA Levelling Screed
•  All works carried out in a live Hospital environment
_____________________________________________________
Regular Clients
• 2000 sq metres Sikafloor EB12 to Cambridge Bunker
•  >4000 sq metres Epoxy Coating to Refurb Industrial Units, London
_____________________________________________________

  • JLR 1
  • JLR 4
  • IMG 4261
  • IMG 4268
  • 1602187220681
  • 1602187218780
  • 1602187217004
  • chelsea pump3

Full Detailed Case Studies to follow

Our office premises and onsite risk assessments continue to be monitored regarding Covid-19 safety allowing us to operate in a safe, controlled environment. This process is a continual improvement, through daily learning.

Whilst looking back on 2020 we can’t stop thinking about those who helped us to build a prosperous business and has been with us throughout the past year. Thank you for your support, may this new year be full of great accomplishments. 

THE SECTORS WE'VE WORKED IN...

Do you have a project in mind? Tell us about your job and get a free site survey.

FOR A QUICK & PROFESSIONAL QUOTE...

IRL are experts in industrial flooring, floor markings, industrial painting and industrial roofing. We will guide you throughout the entire process from preparation, to liaising with your Health and Safety Officer. Get in touch and we will advise you on the best solution for your project.

Contact Us