Another Successful Shutdown Project .....

As a Framework Contractor we were delighted to be awarded the works within Building 50 at the vehicle plant in Oxford.

The work package comprised of isolated floor repairs using Sikascreed BB Slurry and Sika Hardtop 80 Heavy Duty Epoxy Resin Screed followed by Sikafloor 264 Thixo.  The movement joints were reinstated across gangways where visable.

We completed an area of 1925 sq metres during their February 2015 shutdown period.

Testimonial:  Mick Fisher said "will you pass on my thanks to Wayne and his team for their excellent work and commitment to the recoating of black floors in Building 50, this has been a particularly difficult project in the time scale available and the results show the level of effort and flexibility within the team, thanks once again"

THE SECTORS WE'VE WORKED IN...

Do you have a project in mind? Tell us about your job and get a free site survey.

FOR A QUICK & PROFESSIONAL QUOTE...

IRL are experts in industrial flooring, floor markings, industrial painting and industrial roofing. We will guide you throughout the entire process from preparation, to liaising with your Health and Safety Officer. Get in touch and we will advise you on the best solution for your project.

Contact Us